Irish Sea Contractors recently completed a Salvage contract for lift & refloat of mfv “Genna C” which had sunk 1.5 miles NE of Bar Buoy at the entrance to Drogheda Harbour.

The following JW Automarine lift bags were used  during the salvage operation:-

5 x 5 ton Parachute Bags

2 x 5 ton Fully Enclosed Bags

 

The vessel was towed into Clogherhead Harbour with all lift bags inflated on a high tide where a 100 ton crane lifted the vessel onto the quay wall.

Well done to all of  the ISC salvage crew who completed the works within 2 working days in a very professional manner.

 